TAP project 97.9 % completed

Baku, September 19, AZERTAC

At the end of August 2020, the Trans Adriatic Pipeline (TAP) project was 97.9 percent completed, the TAP AG consortium reports.
“TAP is moving closer to completing the project construction phase. In preparation for the start of commercial operation and as part of the testing and commissioning phase, the TAP pipeline has been filled with natural gas from the Greek-Turkish border up to the compressor station in Fier, Albania,” said the consortium.
The Trans Adriatic Pipeline (TAP) AG started to introduce the first natural gas into a 2 km section of the pipeline in Greece between the Evros river and the Kipoi compressor station last November. This is the initial stage of the pipeline commissioning process, which aims to ensure that the infrastructure is entirely safe and ready for operations after the completion of the process, in line with national and international safety and operational standards, according to TAP AG consortium.
Introducing gas into the pipeline system is another milestone towards the start of Shah Deniz 2 gas deliveries to Europe. Commercial gas flows through TAP are being planned to start in October 2020 when the complete asset all the way to Italy is expected to be commissioned and tested.
Following the commissioning of the first section, gas will continue to be gradually introduced into other sections of the Greek pipeline and beyond in Albania and Italy in the upcoming weeks and months.
More than 99 percent of trenching was completed along the Trans Adriatic Pipeline’s (TAP) route, TAP AG consortium earlier reported.
TAP’s first offshore pipelines (7km) in Albania were successfully installed and backfilled in May. This is part of the 105 km section across the Adriatic Sea that will link the gas pipeline to Italy’s transmission network.
The pipes will be laid on the Adriatic seabed: 37 km in Albanian territorial waters, 25 km in Italian territorial waters; and 43 km in international waters.
The 878km long pipeline will connect with the Trans Anatolian Pipeline (TANAP) at the Turkish-Greek border at Kipoi, cross northern Greece, Albania and the Adriatic Sea, before coming ashore in Southern Italy, where it will connect to Italy’s gas transportation grid operated by SNAM Rete Gas.
TAP is the European section of the Southern Gas Corridor, enhancing Europe’s energy security and contributing to decarbonisation and the diversification of gas supplies.
TAP’s shareholders include BP (20%), SOCAR (20%), Snam (20%), Fluxys (19%), Enagás (16%) and Axpo (5%).

Oil & gas 2020-09-19 19:11:00